Inspection and refurbishment of steel gutters to large industrial warehouse

Clientitc5

Royal Mail / ITC Concepts Limited

Project Details

The project involved the high pressure cleaning of the roof slopes to enable a condition survey to be undertaken. The large central box gutters, following cleaning, were identified with defective joints causing leaking. Similarly water ingress was noted around the head and side laps on the roof lights and the roof extract vents.

Product Selection:

Due to the large expanse of roof area and an early morning condensation problem, Belzona 3131 WT Membrane was selected for both the central gutters and the roof lights.

Interesting Facts:

Following erection of the perimeter handrail, the banks of roof lights were then protected with portable protective covers to provide temporary protection while work was carried out.